February 2, 2026

As a reminder, all businesses on Nickel St. are open and accessible.

3rd Ave is currently closed from Nickel St. to the Apartment Parking Lot to the East.

3rd Ave. is open from Marble St. to the apartment parking lot. The section of 3rd Ave between Laurel and Marble is currently closed.

Please use Marble St. to access the apartment parking lot.

Aerial picture of construction on 3rd Ave.
Picture of construction equipment on 3rd Ave.

The panoramic images below provide a 360 degree view of the construction area. You can click and drag the image to look around in any direction.
The thumbnails at the bottom of the window can be clicked to show the area on different dates.

January 19, 2026

As a reminder, all businesses on Nickel St. are open and accessible.

The intersection at Nickel St. and 3rd Ave is currently closed.

3rd Ave. is open from Marble St. to the apartment parking lot. The section of 3rd Ave between Laurel and Marble is currently closed.

Please use Marble St. to access the apartment parking lot.

Picture of construction closing Nickel St.
Picture of construction equipment on 3rd Ave.

January 12, 2026

As a reminder, all businesses on Nickel St. are open and accessible.

The intersection at Nickel St. and 3rd Ave is currently closed.

3rd Ave. is open from Marble St. to the apartment parking lot. The section of 3rd Ave between Laurel and Marble is currently closed.

Please use Marble St. to access the apartment parking lot.

Aerial picture of the Nickel St. Construction
Aerial picture of the closed intersection at 3rd Ave and Nickle St.

January 2, 2026

As a reminder, all businesses on Nickel St. are open and accessible.

The intersection at Nickel St. and 3rd Ave is currently closed.

3rd Ave. is open from Marble St. to the apartment parking lot. The section of 3rd Ave between Laurel and Marble is currently closed.

Please use Marble St. to access the apartment parking lot.

Picture of the closure on Nickel St.
Picture of the open lanes on Nickel St.

December 22, 2025

As a reminder, all businesses on Nickel St. are open and accessible.

The intersection at Nickel St. and 3rd Ave is currently closed.

3rd Ave. is open from Marble St. to the apartment parking lot. The section of 3rd Ave between Laurel and Marble is currently closed.

Please use Marble St. to access the apartment parking lot.

Aerial view of 3rd Ave. and Nickels St.
Aerial view of Nickels St. construction.

December 16, 2025

As a reminder, all businesses on Nickel St. are open and accessible.

The intersection at Nickel St. and 3rd Ave is closed.

3rd Ave. is open from Kohl Ave. to the apartment parking lot.

A picture of the closure of Nickel St. from 1st Ave to 287.
Aerial Image of construction

December 8, 2025

As a reminder, all businesses on Nickel St. are open and accessible.

Nickel St. is closed from 1st Ave. to 287.

3rd Ave. is getting close to reopening from Kohl Ave. to the apartment parking lot.

A picture of the closure of Nickel St. from 1st Ave to 287.
A picture of the paving progress at 3rd Ave at Kohl St.

December 1, 2025

As a reminder, businesses on Nickel St. are open and accessible.

Work continues on 3rd Ave. and the apartment parking lot is accessible.

Aerial picture of construction on 3rd Ave.
Overhead picture showing the construction being done on Nickel St.

November 18, 2025

As a reminder, businesses on Nickel St. are open and accessible.

Work continues on 3rd Ave. and the apartment parking lot is accessible.

All businesses on Nickel are open
Apartment parking lot is open to residents.

November 11, 2025

Nickel St. is closed from 1st Ave. to 3rd Ave.

Work continues on 3rd Ave.  

Nickel St. closed from 3rd Ave to 1st Ave
3rd Ave closed from Apartments to Kohl St.

November 3, 2025

Nickel St. is closed from 1st Ave. to 3rd Ave.

Work constinues on 3rd Ave.  at Marble

Aerial photo showing Nickel St. being closed for construction.
Aerial photo showing construction work at 3rd and Marble.

October 27, 2025

3rd Ave is paved and opened from Garnet St. to Kohl St.

3rd Ave. is closed from Marble to Kohl St. 

Picture of construction on 3rd Ave and Marble St.
Picture of construction on 3rd Ave and Iris St.

October 13, 2025

3rd Ave at Iris is about to be paved and opened to Kohl St.

3rd Ave. at Marble is closed going east.

Picture of construction on 3rd Ave and Marble St.
Picture of construction on 3rd Ave and Iris St.

October 6, 2025

Construction on 3rd Ave.

3rd Ave. from Garnet St. to Iris 

Photo of construction looking west from Kohl St.
Photo of the newly paved road on 3rd Ave. from Garnet St. to Iris St.

September 29, 2025

Construction on 3rd Ave. looking west from Kohl St.

3rd Ave. from Garnet St. to Iris open and freshly paved.

Photo of construction looking west from Kohl St.
Photo of the newly paved road on 3rd Ave. from Garnet St. to Iris St.

September 15, 2025

Construction on 3rd Ave. looking east from Kohl St.

3rd Ave. from Garnet St. to Hemlock St. to open soon.

Construction on 3rd St looking East.
Construction on 3rd St looking East.

September 8, 2025

Construction on 3rd Ave. 

Construction on 3rd St looking East.
Construction on 3rd St looking East.

September 2, 2025

Construction at 3rd Ave. and Kohl St. looking east.

Construction on 3rd St looking East.
Construction on 3rd St looking East.

August 28, 2025

Construction at 3rd Ave. and Kohl St.

Construction at Kohl and 3rd Ave

August 18, 2025

3rd Ave. is closed from Garnett St. to Jade St.

Aerial view of 3rd St. Construction.
Aerial view of 3rd St. Construction.

August 11, 2025

Garnett St. complete and open!

3rd Ave. is closed from Garnett St. to Iris St.

Aerial view of the new construction on 3rd Ave.
Looking east at the construction on 3rd Ave.

August 4, 2025

Garnett St. closed to through traffic from 4th Ave. to Elmhurlt Pl.

3rd Ave. is closed from Garnett St. to Iris St.

Aerial view of the new construction on 3rd Ave.
Looking east at the construction on 3rd Ave.

July 28, 2025

Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

Construction being done on Garnett.
Construction being done on 3rd Ave.

July 22, 2025

Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

Aerial picture of construction on Garnet St.
Aerial picture of the stormwater work being done in the grassy area near the school.

July 7, 2025

Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

Aerial picture of construction on Garnet St.
Aerial picture of the stormwater work being done in the grassy area near the school.

June 30, 2025

Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

Aerial picture of construction on Garnet St.
Aerial picture of the stormwater work being done in the grassy area near the school.

June 16, 2025

Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

June 9, 2025

Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

Installing  the new box culvert.

3rd Ave. has flaggers postioned for access.

Garnett St. is closed from 3rd Ave. to 4th Ave.

June 2, 2025

The main construction project is underway and has Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St.

May 27, 2025

The main construction project is underway and has Garnett St. closed from 3rd Ave. to 4th Ave.

3rd Ave. is also closed from Garnett St. to Iris St. 

May 19, 2025

The waterline work is completed and construction will now begin on the improvements.

All streets are currently open but use caution as portions of 3rd Ave have flaggers directing traffic.

May 12, 2025

Waterline work being done on Nickel St., temporarily closing it from 1st Ave. to 3rd Ave.

3rd Ave. is open but use caution as portions have flaggers directing traffic.

May 5, 2025

Waterline work being done on Nickel St., temporarily closing it from 1st Ave. to 3rd Ave.

April 28, 2025

Waterline work continues on 3rd Ave.

April 14, 2025

Waterline work continues on 3rd Ave. and Marble. Nickel St. is also having some work done. 

April 7, 2025

Waterline work continues on 3rd Ave. 

March 31, 2025

Waterline work continues on 3rd Ave. and some of the benefits of this project are already starting to appear!

March 24, 2025

Taking advantage of Spring Break for some work on Garnet St.
Waterline work continues on 3rd Ave.

March 17, 2025

Pipe lining, waterline lowering, and even some new fire hydrants.

March 10, 2025

Working at the intersection of 3rd Ave. and Hemlock St.