The traffic control plans provided below show how traffic will be impacted during the project in specific areas. Dates may change so check back to ensure the most accurate information.

Emerald Elementary NW Field

This section is currently under construction closing Garnet St. from 4th Ave. to 3rd Ave.

 

Garnet St. from 4th Ave to 3rd Ave

This section is currently under construction closing Garnet Ave. from 3rd Ave. to 4th Ave. 

3rd Ave. from Garnett St. to Hemlock St.

This section is currently under construction closing 3rd Ave. from Garnet St. to Iris St.

Intersection at 3rd Ave and Hemlock St.

This section is currently under construction closing 3rd Ave. from Garnet St. to Iris St.

3rd Ave. from Hemlock St. to Iris St.

This section is currently under construction closing 3rd Ave. from Garnet St. to Iris St.

Intersection at 3rd Ave. and Iris St.

Anticipated closure of this intersection is in August.

3rd Ave. from Iris St. to Jade St.

Anticipated start of construction for this section is mid to late July with a duration of approximately 50 days.

Intersection at 3rd Ave. and Jade St.

Anticipated closure of this intersection is in September.

3rd Ave. from Jade St. to Kohl St.

Anticipated start of construction for this section is early August with a duration of approximately 45 days.

Intersection at 3rd Ave. and Kohl St.

Anticipated closure of this intersection is in September.

3rd Ave. from Kohl St. to Laurel St.

Anticipated start of construction for this section is mid August with a duration of approximately 55 days.

Intersection at 3rd Ave. and Laurel St.

Anticipated closure of this intersection is in October.

3rd Ave from Laurel St. to Marble St.

Anticipated start of construction for this section is early to mid September with a duration of approximately 45 days.

Intersection at 3rd Ave. and Marble St.

Anticipated closure of this intersection is in October.

3rd Ave. from Marble St. to Nickel St.

Anticipated start of construction for this section is late September with a duration of approximately 45 days.

Nickel St. from 3rd Ave to 1st Ave. Phase 1

Anticipated start of construction for this section is in October.

Nickel St. from 3rd Ave to 1st Ave. Phase 2

Anticipated start of construction for this section is in November.

Nickel St from 1st. Ave. to HWY 287

Anticipated start of construction for this section is in November.